GENERAL
The work shall consist of
performing all operations in connection with furnishing, driving, cutting off
and load testing of RCC Cast-In-Situ and Precast Concrete piles to obtain the
specified bearing value, complete in place and strictly in accordance with
these Specifications and as shown on the Drawings.
The kind and type of piles
shall be as shown on the Drawings and/or as specified and shall not be changed,
except with the approval of the Designer.
RCC CAST-IN-SITU PILES
SCOPE OF WORK
All works to be performed under
these Specifications shall be carried out at the proposed locations shown on
the Drawings and shall include but not be limited to the following:
a)
Construction of bored & cast in-situ RC test piles for pile
load tests (Test Pile).
b)
Performance of load tests on piles.
c)
Construction of bored &
cast in-situ RC piles for various structures under contract (working piles).
d)
Performance of proof load tests on the working piles selected by
the Engineer-in-Charge.
e)
Keeping complete record of all
the operations performed during boring, construction and load testing of the
piles stated above.
GENERAL REQUIREMENTS
The general requirements for RC piles shall be as follows:
a)
Type, Diameter and Length of Piles:
i)
Bored cast & in-situ
reinforced concrete (RC) piles using Ordinary Portland Cement (OPC) or Sulphate
Resisting Cement (SRC) as specified shall be constructed as shown on the
Drawings.
ii)
Piles diameter, type and length shall be as shown on the
Drawings.
iii)
Unless the approval of
designer, the contractor cannot change the position, the number, diameter and
length of pile.
b)
Tolerances in Location and Plumbness
Following construction tolerances shall be maintained:
i)
The drilled shaft shall be
within 3 inches of the plan position in the horizontal plane at the plan
elevation for the top of the shaft.
ii)
The vertical alignment of the
shaft excavation shall not vary from the plan alignment by more than ¼ inch per
foot of depth.
iii)
After all the shaft concrete is
placed, the top of the reinforcing steel cage shall be no more than 6 inches
above and no more than 3 inches below plan position.
iv)
When casing is used, its
outside diameter shall not be less than the shaft diameter shown on the plans.
When casing is not used, the minimum diameter of the drilled shaft shall be the
diameter shown on the plans for diameters 24 inches or less, and not more than
1 inch less than the diameter shown on the plans for diameters greater than 24
inches.
v)
The bearing area of bells shall
be excavated to the plan bearing area as a minimum. All other plan dimensions shown
for the bells may be varied, when approved, to accommodate the equipment used.
vi)
The top elevation of the shaft shall be within 1 inch of the
plan top of shaft elevation.
vii)
The bottom of the shaft
excavation shall be normal to the axis of the shaft within ¾ inch per foot of
shaft diameter.
c)
Cutting of Pile Heads:
Pile heads shall be cut to the
levels shown on the Drawings and the cut shall be level, smooth, and
horizontal. Due care shall be taken to protect the edges and reinforcement. No
extra payment shall be made for this work. Pile cut off levels shall be shown on
the shop drawings to be submitted by the Contractor for approval of the
Engineer-in-Charge.
d)
Order of work:
The order in which construction
and load testing of piles shall be carried out will be decided by the
Engineer-in-Charge, who will have the discretion to alter the same during the
course of the work.
e)
Plant:
The Contractor shall keep on
the site sufficient plant to meet all requirements of the work. The plant shall
be in satisfactory operating condition and capable of efficiently performing
the work as per these Specifications.
f)
Supervisory Staff:
The Contractor shall have at
site at all times, only qualified, experienced and thoroughly competent
persons, who shall conduct and supervise drilling, pile construction and load
testing operations. Since the construction of piles requires special knowledge
and utmost care, the Contractor shall have at least one qualified and experienced
Engineer-In-charge specialized in this field of work who shall be present full
time during execution. The Contractor shall remove from the site any employee
who does not in the opinion of the Engineer-in-Charge, meet these requirements.
g)
Site Conditions:
The Contractor is responsible
for any damage to the existing superstructures, sub-structures utility lines
caused due to piling work. The contractor shall ensure that pile construction
works shall not interfere with the work of the other Contractors working in the
area.
Where approval has been given
to the Contractor for carrying out concreting operations at night or in places
sunshine hours are limited, the Contractor shall provide adequate lighting at
all points where mixing, transporting, placing of concrete is in progress.
When concrete is to be
manufactured, transported and placed in hot weather, specific precautions as
required by the Engineer-in-Charge shall be observed in accordance with the
provisions of sub-sections 5.3.2.5(f) and 5.3.4(c).
h)
Quality Assurance:
Quality of concrete for piles shall comply with Section5 – Plain
& Reinforced Concrete.
The materials, used in pile
construction (cement, aggregates, steel reinforcement etc.) shall conform to
the requirements of relevant Sections of technical provisions.
Standards and Codes of Practice:
The latest edition of
International Standards and codes such as American, British or German etc.,
shall be used. All materials and workmanship shall, unless otherwise specified,
comply with these standards and codes.
The Contractor shall make
available at the site for the use of the Engineer-in-Charge, one copy of each
of all relevant Standards & Codes used and quoted in the documents and
Drawings at his own expense. No additional cost will be paid to the contractor
for this.
SUBMITTALS
The Contractor shall be required to make following submittals:
1)
Method Statement:
The Contractor shall submit to
the Engineer-in-Charge before start of piling work a detailed description of
the equipment, materials and procedures that will be used. The description
shall include equipment specifications, loading capacities, protective devices,
test apparatus, detailed installation procedures, test procedures and other
documents ordered by the Engineer-in-Charge. Contractor's construction
procedures shall be type-written and shall include charts and diagrams as
applicable and necessary, to fully explain the subject procedures, methods and
equipment operation in order to allow effective review by the
Engineer-in-Charge. The method statement shall be submitted to the Engineer at
least 2 weeks prior to commence the work.
2)
Survey and Location:
The Contractor shall carry out
a levelling survey and provide excavated ground elevations for each pile
location. The elevations shall be given with respect to a permanent Bench Mark.
The locations of piles shall be established by the Contractor as per shop
drawings as approved by the Engineer-in-Charge. Establishing the pile
locations accurately in the field shall be the sole responsibility of the
Contractor.
3)
Protective Measures:
The Contractor shall submit to the Engineer-in-Charge procedures
for the following:
a)
Both hot and cold weather
concreting procedures shall be submitted to the Engineer-in-Charge by the
Contractor regardless of the need for the immediate implementation of such
procedures. Procedures shall include insulation, enclosures and the like,
finishing procedures and timing and duration of curing shall be described.
b)
Protection of concrete against
damage due to mechanical contact and construction operations,
c)
Proposal regarding necessary
facilities for drainage of the excavated areas, It shall be the Contractor's
sole responsibility to keep the site free of pounding water during rain and
during boring and construction of piles.
4)
Placement Schedule:
The Contractor shall submit a
placement schedule for review prior to start of concrete placement operations.
Daily concrete pour schedules shall be submitted 24 hours in advance of planned
pours.
5)
Testing Programme:
The Contractor shall submit
test programme for all specified requirements along with the testing schedule.
6)
Test Reports:
The Contractor shall submit
test reports showing the results of required tests and compliance with
specified standards and codes. Test reports shall be certified by the
Contractor at the testing agency approved by the Engineer-in-Charge.
7)
Samples:
The Contactor shall submit to
the Engineer-in-Charge for acceptance prior to purchase, fabrication or
delivery samples of materials or products where required by the
Engineer-in-Charge.
Substitute products, materials
or fixtures proposed by the Contractor shall be submitted as samples to the
Engineer-in-Charge for his information about materials.
8)
Shop Drawings:
The Contractor shall submit for
Engineer-in-Charge a review and acceptance detailed shop drawings showing
layout, arrangement, dimensions locations of piles, pile diameters and lengths,
pile marks and details of construction showing reinforcement of the piles. The
drawing shall also indicate the cut off level, tip elevation of each pile and
all other necessary details required for completion of the construction work or
required by the Engineer-in-Charge. Shop drawings shall be submitted to the
Engineer-in-Charge for his acceptance and approval.
PRODUCTS
The products and
materials shall meet the following requirements.
1.
General:
All materials used in the Works
shall be subjected to inspection and testing as and when directed by the
Engineer-in-Charge.
Should the Engineer-in-Charge
decide not to carry out tests on a material or materials himself or under his
direction, the Contractor shall, whenever required, obtain from the
Manufacturer and submit to the Engineer-in-Charge the certificates, showing that
tests of materials having been carried out in accordance with the requirements
of this Specification. Engineer-in-charge can verify the test reports in his
own presence or his representative.
Before ordering any materials
proposed to be used in the execution of the Works, the Contractor shall submit
to the Engineer-in-Charge for his written approval the name(s) and address(es)
of the firm(s) from which he proposes to order the material(s).
If the Engineer-in-Charge is in
doubt about the quality of the delivered materials, the Contractor shall
demonstrate through the relevant tests that the quality of the materials fully
satisfies the requirements of this Specification.
2.
Concrete:
Concrete for bored &
cast-in-situ pilesincluding their caps, shall be in accordance with the
requirements specified in the Section 5 - Plain Reinforced Concrete using
Ordinary Portland Cement (OPC) or Sulphate Resisting Cement (SRC) as
specified.In addition to meeting the strength requirements, the concrete for
bored & cast in-place piles shall have adequate workability for the method
of placing employed in the casting of piles and the consistency will meet the
requirement as stipulated in the Section as above.
The concrete shall be supplied
in sufficient quantity to ensure that the concreting of each cast in-place pile
proceeds without interruption.The concrete shall be of class as specified in
accordance with the Specifications and Drawings.
3.
Concrete Aggregates:
Coarse and fine aggregates used
for concrete under these Specifications shall be furnished by the contractor in
accordance with the provisions of and in complete conformity with the
requirements of the Specifications in Section 5 – Plain & Reinforced
Concrete.
4.
Reinforcing Steel:
Reinforcing steel shall conform
to the requirements set forth in Sub-section 5.4 – “Concrete Reinforcement” of
the Section 5 – Plain & Reinforced Concrete. All placing shall be in
accordance with the Drawings furnished or as approved by the
Engineer-in-Charge.
5.
Drilling Fluid:
The drilling fluid used for all
types of drilling shall be clean water, free from suspended sediments. The
Contractor may be allowed to use bentonite slurry, barite slurry, loss
circulation material as drilling fluid with the prior approval of the Engineer-in-Charge.
6.
Casing of Holes:
Casing of holes shall be according to the provisions given
below:
a)
The hole shall be cased up-to its bottom.
b)
The casing shall be made of cylindrical steel pipes of inside
diameter equal to the pile diameter and shall have
sufficient strength so as to maintain position and shape during drilling
operations. Casing used during concreting should be free from internal
projections and encrusted concrete which might prevent the proper formation of
piles. It shall also be free from distortion and shall be of uniform
cross-section throughout.
c)
The casing may be omitted only
where it can be shown to the satisfaction of the Engineer-in-Charge that
lowering of reinforcement cage and concreting operations will not cause caving
of the bore hole.
d)
It shall be the Contractor's
responsibility to pull out the casing from the holes at the time of concreting
of piles. No extra payment shall be made for pulling out the casing or for
leaving the casing inside the hole.
EXECUTION
The procedures for execution shall be as follows:
1)
Drilling:
Drilling shall be performed as described below:
a)
General:
i)
Before starting the piling
work, the contractor shall complete clearing, leveling and setting out of the
site. Any obstacles shall be removed, as directed by the Engineer-in-Charge. If
the presence of existing underground utilities is known or suspected, the
Contractor shall carry out such diversion or protection of these as directed by
the Engineer-in-Charge.
ii)
All excavations shall be
carried out as nearly as possible to the exact dimensions of the pile
foundations to minimize back filling.
iii)
All surplus excavated material
from excavations not required for back filling shall, if considered unsuitable
by the Engineer-in-Charge, be disposed of as directed.
iv)
All installation procedures
shall be subject to the Engineer-in-Charge's approval. No pile boring shall
take place within 48 hours of the concreting of any pile which is within a
radius of 10 feet (3.05 meters).
v)
The sequence of work shall be
proposed by the Contractor and as approved by the Engineer-in-Charge. The test
piles shall be constructed and load-tested prior to the start of main piling.
Additionally, proof load tests shall also be carried out on working piles
during construction of piles. The piles for proof load tests shall be selected
by the Engineer-in-Charge.
b)
Method of Drilling:
The drilling of holes for
piling shall be done by straight or reverse rotary rig or any other suitable
method proposed by the Contractor, subject to approval of the
Engineer-in-Charge. Regardless of the method used for drilling holes, the
following specifications shall be adhered to by the Contractor.
i)
After completion of drilling operations the bore hole length shall
be checked and recorded.
ii)
The deviation from the vertical
shall not exceed 0.5 degree (1 in 114) on any section of the length for the
holes.
iii)
Drilling operations shall be
carried out in such a way as to avoid any disturbance of the soil especially at
the bottom of the hole. (i.e., sand boiling).
c)
Stabilizing the Holes:
The Contractor
shall ensure at all times that the hole does not collapse during and after
boring. The Contractor may use bentonite slurry or any other drilling method
with written approval of the Engineer-in-Charge. When bentonite slurry is used
strict compliance with Sub-section-f herein below shall be ensured. The nominal
diameter of pile is defined as the minimum cross-section of unlined portion of
borehole. The possible enlargement of the pile shaft during boring, placement
and compaction of the concrete, shall not be taken for measurement and for
increase in the admissible load. It may also be noted that no extra payment
shall be made for using bentonite slurry or adopting alternative drilling
method(s) for advancing the boreholes in satisfactory manner.
d)
Removal of Mud:
The excavated
material from boreholes shall be disposed of by the Contractor under
instructions of the Engineer-in-Charge at no extra cost.
e)
Clean out and Control at the Bottom of the Piles:
After the bore has reached its
final penetration as stipulated on the Drawings and as may be additionally
ordered by the Engineer-in-Charge, on the basis of data obtained in the field,
and after it has been completely cleaned of all earth and otherwise made ready
to receive the reinforcement and thereafter the concrete, the Contractor shall
so inform the Engineer-in-Charge. All disturbed soil and loose materials shall
be pumped out in such a manner that after cleanout operation, the bottom of
borehole remains horizontal and in undisturbed condition. The clean out pumping
arrangement shall be such that the lower end of the pump can be moved all over
the cross-section by a routine operation. The suction of the pump shall be
adjustable.
At the end of clean-out operations, a break shall be made for a
period of at least five minutes, then pumping shall be resumed and shall
continue until the bottom of hole is cleaned. The Engineer-in-Charge shall
check the actual bore penetration achieved, the cleanliness of the boreholes
and the amounts and directions, if any, by which the borehole is out of
position and/or out of plumb and having satisfied himself on these and on any
other points which he may consider relevant, shall sign pour slip for the
borehole authorizing the Contractor to proceed with the placing of
reinforcement. The Contractor shall under no circumstances proceed with the
placing of reinforcement in the boreholes or with the subsequent concreting
without having first obtained the written authority signed separately for each
and every borehole.
f)
Bentonite Slurry:
Where the use
of bentonite slurry is approved for the purpose of maintaining the stability of
the walls and base of bore, the Contractor's proposals in accordance with
clause (v) herein below shall include details of the slurry. These shall
include inter-alia.
•
The source of the bentonite
•
The constitution of the slurry
•
Specific gravity, viscosity, shear strength and pH value of
slurry.
•
The methods of mixing, storing, placing, removal and
recirculating the slurry, and
•
The provision of stand-by equipment.
i)
Tests shall be carried out to
ensure that the proposed constitution of the slurry is compatible with the
ground water: Proposals for the constitution and physical properties of the
slurry shall include average, minimum and maximum values. The specific gravity
of the slurry shall not be less than one and one tenth (1:1/10) in any case at
any time. The Contractor shall use additives where necessary to ensure the
satisfactory functioning of the slurry.
ii)
A manufacturer's certificate
showing the properties of the bentonite powder shall be delivered to the
Engineer-in-Charge for each consignment delivered to site: Independent tests
shall be carried out at laboratory approved by the Engineer-in-Charge on
samples of bentonite frequently.
iii)
The Contractor shall carry out tests at site during the course
of the piling to check the
physical properties of the bentonite slurry in the works. These
tests shall include, inter-alia, density, viscosity, shear strength and pH
tests. The test apparatus and test methods shall be proposed by Contractor as recommended by
manufacturer and as approved by the Engineer-in-Charge.
iv)
The frequency of tests shall be
that which the Contractor considers necessary to ensure that the bentonite
slurry is in accordance with his proposals and as such other times as the
Engineer-in-Charge may direct.
v)
Should the physical properties
of any bentonite slurry deviate outside the agreed limits, such slurry shall be
replaced, irrespective of the number of times it has been used by new bentonite
slurry of correct physical properties. Adequate time shall be allowed for
proper hydration to take place consistent with the method of mixing, before
using slurry in the works.
vi)
The Contractor shall control
the bentonite slurry so that it does not cause a nuisance either on the site or
adjacent waterway or other area. After use it shall be disposed of in a manner
approved by the Engineer-in-Charge.
vii)
The level of the slurry in the
bentonite shall be maintained so that internal fluid pressure always exceeds
the external water pressure.
viii)
If chiselling is used when
boring through hard strata or to overcome obstructions, the stability of the
excavation shall be maintained by methods acceptable to the Engineer-in-Charge.
2)
Concreting:
Concreting of piles shall be done as given herein below:
a)
Placing of Steel Reinforcement:
The cage of reinforcement shall
be assembled on the ground and securely tied by means of binding wire in such a
manneras to form a rigid cage. It shall be lowered in the bore hole carefully
keeping the cage concentric with the bore hole. Adequate concrete spacers shall
be provided around the cage to ensure the required concrete cover to be
available on all sides of the cage. Concrete spacer blocks specially pre-cast
for this purpose shall be securely attached to the reinforcement at a suitable
spacing and each quarter point so as to ensure that the concrete cover
stipulated on the drawings is maintained throughout and that the reinforcement
cage is not displaced in the casing during the course of subsequent concreting
operations. In addition concrete spacer blocks shall be located immediately
below and immediately above the lap at 4 points spaced around the cage.
Particular care shall be taken to ensure that none of the spacer blocks move
out of position to the inside of the reinforcement cage due to spacer blocks or
lapped reinforcement or any other reasons which might interfere with concrete
placement. Depth of the hole shall be measured just before and after the
lowering of cage. In case it is found that the soil has caved into the hole
during the lowering of the cage, the contractor shall be required to adequately
clean the hole to the satisfaction of the Engineer-in-Charge, before the start
of concreting at his own cost.
b)
Composition of Concrete:
Composition of concrete shall be as specified.
c)
Batching of Concrete:
Batching of concrete shall be
in accordance with the provisions of Section 5 – Plain & Reinforced
Concrete.
d)
Mixing of Concrete:
Mixing of concrete shall be
done in accordance with the provisions of Section 5 – Plain & Reinforced
Concrete.
e)
Conveying:
Concrete shall be conveyed from
mixer to piles as rapidly as practicable by methods which will prevent
segregation or loss of ingredients, as specified in Section 5 – Plain &
Reinforced Concrete. Any wet batch hopper
through which the concrete passes shall be conical in shape. There shall be no
vertical drop greater than 5 feet. Belt conveyers, chutes, or other similar
equipment will not be permitted for conveying concrete except where the use of
such equipment is approved in writing by the Engineer-in-Charge, in advance of
any use.
g)
Placing:
i)
General
Once the bore hole has reached
the required depth and the reinforcement cage properly installed, and such
depth has been checked and recorded concreting operations shall be carried out.
Approval of the Engineer-in-Charge shall be obtained before starting any
concrete pour. Concrete pouring will not be permitted when in the opinion of
the Engineer-in-Charge weather conditions prevent proper placement. Unless
otherwise approved concrete pouring shall be performed only in the presence of
a duly authorized representative of the Engineer-in-Charge.
ii)
Mixing-Placing Interval:
Concrete shall be placed within thirty minutes, after it has
been mixed.
iii)
Placing Temperature:
Concrete shall be delivered to
the piles at the coolest temperature which is practicable to produce under
current conditions but in no case at a temperature in excess of 90°F (32°C) or
lower than 41 of (5°C).
iv)
Placing Method
Pouring of concrete shall be done by an
efficient tremie technique. The method and equipment used shall be subject to
the prior approval of the Engineer-in-Charge. The tremie pipes shall have to be
large enough with due regard to the size of the aggregate. For 3/4 inches (19.5
mm) aggregate, the tremie pipe shall be of diameter not less than 6 inches (15
mm) and for larger aggregate, larger diameter tremie pipes shall be used. The
hopper and tremie pipe shall have to be a closed system embedded in the placed
concrete, through which water cannot pass. When concrete is deposited by
tremie, the tremie seal shall be effected in a manner which will not produce
undue turbulence in the water around the pipe. The discharge end shall be kept
submerged continuously in the concrete and the shaft kept full of concrete to a
point well above the water surface. The tremie shall not be moved horizontally
during a placing operation. The rate of placing concrete in the borehole shall
be neither less than 30 feet (9.15 meters) per hour and nor more than 50 feet
(15.24 meters) per hour.
When a casing is used, it shall
be lifted up-to height less than the height of casing already filled in with
concrete. The bottom of casing shall stop to an elevation of 5 feet (1.52
meters) lower than the top of the concrete. Particular care shall be taken in
order to avoid earth slide inside the hole.
During the progress of pouring,
the Contractor will ensure that a stand by equipment is available in order to
cope with plant break down if encountered.
.
The Contractor shall not be
permitted to place concrete while it is raining. Should it rain while the
concrete placement is already in progress, the Contractor shall carry on with
proper and sufficient precautions, the concrete placement operation until the
pile is completed and shall cover the concrete already placed and under setting
condition with polythene or similar impervious sheets. No additional payment
shall be made for any such emergency and protection works.
All tremie tubes shall be scrupulously
cleaned after use for subsequent concreting.Concrete in piles shall be
continued up-to two feet above cut off levels as shown on the Drawings and
shall be broken down to cut-off levels prior to placement of pile caps. The
contractor shall break back the concrete in the top
portion of the piles to the final elevation which will be 3 inches above the
bottom of the pile cap and at the same time exposing the length of pile
reinforcement required for lapping and binding with the pile cap. The
contractor shall also establish and record the actual co-ordinates of the
centres of the broken-off pile tops with respect to theoretical centre line of
each pile cap as shown on the Drawings and the tolerance in this respect shall
not exceed 2 inches (50 mm) in any direction. No separate payment will be made
for manufacturing, placing and breaking of this part of concrete.
v)
Protection and Curing
As each pile cap is completed,
the projected length shall be immediately and carefully protected from any
condition that will damage or adversely affect the hardening of concrete.
Concrete shall be cured for 28 continuous days by an approved method.
vi)
Stripping and Finishing
Any cracked or defective
concrete in the head of the completed pile shall be cut away and made goodwith
new concrete well bonded into the old. The reinforcement in the pile shall be
exposed for a sufficient distance to permit it to be adequately bonded to the
pile cap. This shall be done carefully to avoid shattering or otherwise
damaging the rest of the piles. The reinforcement shall then be cleaned and
bent to form an anchorage into the concrete of the super-structure as directed
by the Engineer-in-Charge.
Where a temporary casing is
used, the top of the pile shall be brought up sufficiently above the required
finished level to allow for slumping on withdrawal of the casing and to permit
all laitance and weak concrete to be removed.Particular attention shall be paid
to the compaction of the concrete in the top 3 feet (0.91 meters) or so of the
pile.
vii)
Damaged Piles
Should any pile be damaged or
not conforming to the requirements of this Specification the Contractor shall
be responsible for repairing or replacing the pile to the requirements and
satisfaction of the Engineer-in-Charge without cost to the Employer.
Should the Engineer-in-Charge
doubt the efficiency of any pile so repaired, he may order the Contractor to
construct additional piles, at points selected by him without cost to the
Employer. The Engineer-in-Charge may direct the Contractor to proof load test
the doubtful pile.Any piles that are damaged or imperfect and thus rejected by
the Engineer-in-Charge shall be removed and discarded.
When the rejected pile is
withdrawn, the space shall be filled solid with gravel or broken stone without
extra payment therefore.Debris from pile cut-offs and damaged piles shall not
be buried in required fill under slabs at grade or in required embankments but
shall be disposed of by the Contractor off the site of the work.Piles which, in
the opinion of the Engineer-in-Charge, are defective in any way shall be
rejected and replaced by the Contractor without any extra cost.
viii)
Safety Precautions
Before commencing piling
operations, reference shall be made to Pakistan statutory safety requirements.
In addition, the safety precautions in British Standard CP 2004 shall be
strictly followed.The presence of the gas mains, electric cables, water mains and
other services that may be damaged and cause injuries shall be investigated
before work is commenced. The site shall be kept clear of dangerous
obstructions.
High tension overhead power
lines shall not be approached nearer than 15 feet (4.57 meters) because of the
danger of sparking.A safety supervisor shall be appointed on site, the
supervisor being qualified in accordance with the statutory regulations.
First-aid boxes in the charge of a responsible person
shall be kept at all the locations.Fencing shall be provided to prevent free
access to the site and all open pits and boreholes shall be covered.
If lighting by electricity is provided, it is preferable that the voltage for trailing cables shall not exceed 60 V. Electrical installations shall be properly earthed. Cables shall be protected from accidental damage and kept clear of movable equipment plugs and socket connections shall be of water- proof type.Safety helmets and safety footwear shall always be worn by all workers. Piling sites are often wet and use of rubber boots shall be essential.
All boring and concreting equipments shall be cleaned regularly.Helmets, driving caps, etc., shall be inspected regularly for damage or fracture.If cast in-place piles are finished below ground level, proper covers shall be provided to prevent workmen from falling into the holes.
If lighting by electricity is provided, it is preferable that the voltage for trailing cables shall not exceed 60 V. Electrical installations shall be properly earthed. Cables shall be protected from accidental damage and kept clear of movable equipment plugs and socket connections shall be of water- proof type.Safety helmets and safety footwear shall always be worn by all workers. Piling sites are often wet and use of rubber boots shall be essential.
All boring and concreting equipments shall be cleaned regularly.Helmets, driving caps, etc., shall be inspected regularly for damage or fracture.If cast in-place piles are finished below ground level, proper covers shall be provided to prevent workmen from falling into the holes.
LOADING TESTS ON PILES
The procedure for loading test on piles shall be as given below:
a)
Pile load tests shall be
conducted to failure on test piles prior to commence actual piling work. The
number and location of test piles shall be given by the Engineer-in-Charge in
thefield. Test piles shall be constructed 'first, cured for 28 days and then
load tested for load carrying capacity by the procedure specified in ASTM
D1143.
Proofload tests shall be
conducted on selected working piles during and after execution of piling work
of the constructed piles. The number of proof load tests, selection of proof
load test pile, and magnitude of load shall be decided by the
Engineer-in-Charge. The proof load should be 150% of design load.In case of
failure of a working pile it shall be considered as a damaged pile to be
replaced by another pile at no extra cost to the Employer.
b)
The Contractor shall be
responsible for bringing all equipment and supplies to the site for
satisfactory performance of the test according to ASTM D1143, or any other
method approved by the Engineer-in-Charge.
c)
The Contractor shall submit to
the Engineer-in-Charge an up-to-date calibration certificate from a laboratory
approved by the Engineer-in-Charge, showing correctness of the gauge and/or
load cell to be used with the hydraulic jacks.
d)
The apparatus shall be calibrated
as per requirements of ASTM D1143. The Contractor shall submit to the
Engineer-in-Charge details of calibration within 7 days prior to commencing
testing for his review and approval.
e)
The pile head shall be cut-off
or built up to the necessary elevation and shall be capped appropriately to
produce a horizontal bearing surface.
f)
Care shall be taken to ensure
that the center of gravity of the kentledge is on the axis of the pile and that
the load applied by the jack is coaxial with the pile.
g)
Settlement of pile head shall
be recorded using dial gauges and precise levelling in accordance with ASTM
D1143.
h)
The record of pile load test
shall be kept on an approved format as given in Forms-1 to 3 of these
specifications. The Contractor shall prepare load-time settlement curves for
each such load test. Two copies of the relevant field data and the graphs shall
be supplied to the Engineer-in-Charge within 48 hours of the completion of the
test.
RECORD AND REPORT
The following tests, records and reports shall be prepared by
the Contractor at his own
expense.
1)
Records:
The Contractor shall keep
accurate records of all the works accomplished under this Section. All such
records shall be preserved in good condition and order by the Contractor until
they are delivered and accepted by the Engineer-in-Charge. The
Engineer-in-Charge shall have the right to examine such records at any time
prior to their delivery to him.
The following information
shall be included in the records for each pile.
a)
Pile number and elevation of top of bore hole and top of pile.
b)
Type of rig used and a brief description of drilling operations.
c)
Type of soil encountered in the hole with values of cohesion and
angle of internal friction.
d)
SPT resistance values (N-values)
e) Date and depth of bore when drilling operations were performed
and piles constructed.
f)
Total depth of each bore hole.
g)
Size and length of casing, if used.
h)
Quantity of concrete and steel used for the construction of each
pile.
i)
Quantity of constituents for
each batch of mix, water cement ratio and the result of all quality control
tests.
j)
Date and time of load testing
of piles, load and settlements readings during the loading and unloading of the
test piles (For test piles only).
k)
Graph of time-load-settlement relationship for test (For test
piles only).
l)
Remarks concerning any unusual
occurrence during drilling, concreting and load testing of piles.
2)
The presence of
Engineer-in-Charge's representative or the keeping of separate records by his
representative shall not relieve the Contractor of the responsibility for the
work specified in this clause. Payment will not be made for any work for which
records have not been furnished by the Contractor
3)
Reports:
Reports of each pile
construction and pile load test shall be communicated to the Engineer-in-Charge
as follows:
a)
Oral reports as the work proceeds.
b)
A report in duplicate not later
than 48 hour after the completion of each hole, concreting of piles and load
testing of piles. Performa record of piling work for pile load test record is
enclosed as Form-2 and Form-3.
c)
Daily record for bored piles on the format shown in Form-1.
d)
Five copies of the final report of the works within one month of
completion of the last pile.
4)
The final report shall include:
a)
Layout showing the
"As-built" arrangement of piles, their exact locations, dimensions,
length, reinforcements, cut off elevation and the location of test piles.
b)
A tabulation of the loads and
settlement readings during the loading and unloading of the test piles
c)
A graphic representation of the test results in the form of
time-load-settlement curves.
PRECAST CONCRETE PILES
GENERAL
The general requirements of
Precast concrete piles shall comply with sub-section 7.2.2 unless otherwise
specified hereof and approved by the Engineer-in-Charge. The submittals shall
comply with Sub-section 7.2.3 and products for production of reinforced
concrete piles shall comply with Sub-section 7.2.4 Sub-paras (1) to (4).
MANUFACTURE
The concrete and reinforcing
steel for manufacture of precast piles shall be produced and placed according
to the applicable provisions of Section 5 – Plain & Reinforced Concrete. All concrete load bearing plies
shall be manufactured in accordance with the details shown on the drawings or
as directed by the Engineer-in-charge in writing. The plies shall be cast on
level, and tight platforms shall be constructed to prevent settlement during
the casting and curing operations; All concrete shall be thoroughly compacted
by adequate vibration, spading and roding during the placing operation, and
shall be thoroughly worked around the reinforcement and Into the corners of the
forms. Vibrations shall be applied uniformly over the entire length of the pile
and shall be of sufficient duration to ensure a thorough compaction. Pick-up
points and date of casting shall be distinctly marked on each pile.Unless
otherwise specified. or directed by the Engineer-In-charge in writing the
dimensions of the plies shall be as shown on the approved drawings.
PILE SHOES
Pile shoes when required shall
be of the design as called for on the Drawings or directed by the
Engineer-in-Charge.
STORAGE AND HANDLING
Storage and handling of the
plies shall be executed In a way that does not subject them to over-stress,
spalling or other Injuries. Piles shall remain undisturbed after casting and
shall not be subjected to handling till the specified curing period ends. They
shall be lifted by means of a suitable bridle or slings attached to them at the
marked pick-up points. Piles which are over-stressed or otherwise Injured
during curing or handling shall be removed away from the site of work by the contractor
at his own expense.
PLACING OF PILES
Plies shall be driven as
accurately as practicable in the correct location, true to line both laterally
and longitudinally and to the vertical line as indicated on the drawing. A
lateral deviation from the correct location at the cut-off elevation of not more
than 3 inches shall be permitted. A variation in slope of not more than 2
Inches per 10 feet of longitudinal axis shall only be permitted. The correct
relative position of piles shall be maintained by the use of template or by
other approved means. Any pile driven out of correct locations shall be pulled
out and re-driven by the contractor at no additional cost. No lateral force of
any nature or magnitude shall be permitted to pull a pile into correct position
or vertical alignment.
DRIVING OF PILES
PILE LENGTH
The criteria for pile length
and bearing capacity will be determined by the Engineer according to the
results from test piles and load tests. The piles shall be driven to such
depths, that the bearing loads indicated on the Drawings are obtained.
The criterion for pile length may be one of the following:
1.
Piles in sand and gravel shall
be driven to a bearing value determined by use of the pile driving formula or
as decided by the Engineer-in-Charge.
2.
Piles in clay shall be driven
to the depth ordered by the Engineer-in-Charge. However, the bearing value
shall be controlled by the pile driving formula if called for by the
Engineer-in-Charge.
3.
Piles shall be driven to
refusal on rock or hard layer when so ordered by the Engineer-in-Charge.
The Contractor shall be
responsible for correct pile lengths and bearing capacities according to the
criteria given by the Engineer-in-Charge.
PILE DRIVING
Plies shall be driven by means
of a steam hammer or an air hammer of a size and type suitable for the work, as
approved by the Engineer-In-charge. The weight of the moving parts of the hammer shall not be less than
8000 pounds, unless otherwise authorized by the Engineer-In-charge. The hammer
shall be operated at all times at the steam or air pressure and at the speed
recommended by the manufacturer. Boiler or compressor capacity shall be
sufficient to operate the hammer continuously at full rated speed.
During driving, piles shall be protected by a cushion and cap approved by the
Engineer-In-charge. Pile drivers shall have firmly supported leads extending to
the lowest point the hammer must reach to drive the piles to cut-off elevation
without the use of a follower.
Each pile shall be driven continuously and
without voluntary Interruption till the required depth of penetration has been
attained. Deviation from this procedure shall be permitted by the
Engineer-In-charge only in case the driving is stopped by causes which could
not reasonably have been anticipated. Water Jet shall be allowed to be used to
assist driving only when specifically authorized by the Engineer-in-charge, who
shall grant such permission only where satisfactory driving cannot be obtained
otherwise. Where jetting is authorized, the Jetting equipment shall be of a
type and capacity approved by the Engineer-In-charge. The lowest 3 feet shall
however, be always driven without jetting. Unless otherwise authorized by the
Engineer-in-charge no pile shall be driven within 100 feet of concrete less
than seven days old. Unless otherwise specified or directed by the
Engineer-in-charge all pile tops shall be driven to cut-off elevation.
PILE DRIVING FORMULAS
Pile driving formulas may be used to determine the number of
blows of hammer per unit of pile
penetration needed to obtain
the specified bearing capacity for piles driven in the sub-soils at the site.
Piles shall be driven to a final resistance as indicated on the plans
determined by the following formula:
For Drop Hammer
Qall = WH/[6(S+2.5)]
For single-acting steam or air
hammers and for diesel hammers having unrestricted rebound
of
rams.
|
||||||||
Qall
|
=
|
WH/[6(S+2.5)]
|
(Use
when driven
|
weights
|
are
|
smaller
|
than
|
|
striking
weights)
|
||||||||
Qall
|
=
|
WH/[6{S+0.25(WD/WS)}]
|
(Use
when driven
|
weights
|
are
|
larger
|
than
|
|
striking weights)
|
||||||||
For double-acting steam or air hammers and for diesel
hammers having enclosed rams.
|
||||||||
Qall
|
=
|
E[6(S+2.5)]
|
(Use
when driven
|
weights
|
are
|
smaller
|
than
|
|
striking
weights)
|
||||||||
Qall
|
=
|
E[6{S+0.25(WD/WS)}]
|
(Use
when driven
|
weights
|
are
|
larger
|
than
|
|
In the
above formulas:
|
striking weights)
|
|||||||
Qall
|
=
|
Allowable
pile load in Kilograms.
|
||||||
W
|
=
|
Weight of striking
parts of hammer in Kilograms.
|
H
= The height of fall in
centimetres for steam and the observed average height of fall in centimetres of
blows used to determine penetration for diesel hammers with unrestricted
rebound of hammer.
S
= Average net penetration per
blow in centimetres for the last 10 to 20 blows of steam, air, or diesel
hammer, or for the last 15 centimetres of driving for a drop
hammer.
|
||
E
|
=
|
The
actual energy delivered by hammer per blow in Kilogram centimeter
|
WD =
|
Driven weights in
Kilogram
|
|
Note:
|
Ratio of driven weights
to striking weights should not exceed three.
|
|
WS
|
=
|
Weight of striking
parts in Kilo grams.
|
Modifications of basic
pile driving formula:
a)
For piles driven to and seated
in rock as high capacity end-bearing piles: Drive to refusal (approximately
four(4) to five(5) blows for the last 0.625 centimeters of driving). Re-drive open end pipe piles repeatedly until
resistance for refusal is reached within two and half (2.5) centimeters of
additional penetration.
b)
For piles driven through stiff
compressible materials unsuitable for pile bearing to an underlying bearing
stratum:
Add blows attained before
reaching bearing stratum to required blows attained in bearing stratum.
c)
For piles into limited thin bearing stratum:
Drive to predetermined tip elevation, and determine allowable
load by load test.
The bearing power as determined
by the appropriate formula in the foregoing list will be considered effective
only when it is less than the crushing strength of the pile. Other recognized formula for determining pile bearing power may be used when given in special
specification. However, it shall be understood that the relative merits and
reliability of any of the pile formula can be judged only on the basis of
comparisons with the results of load tests.
DAMAGED AND MISPLACED PILES
Any pile which is cracked or broken because
of internal defects or by improper handling or driving or which Is otherwise
Injured so as to Impair it for Its intended use or any pile driven out of
proper location shall be removed and replaced by the contractor at his own
expense. The Engineer-in-charge may require the contractor to pull out certain
selected plies (up to a maximum of 2 per cent of the total number of the plies
driven subject to a minimum of 2 plies) for test and Inspection to determine
their condition. Any pile so pulled out and found to be damaged to such an
extent as, In the opinion of the Engineer-In-charge, would Impair Its
usefulness In the completed structure, shall be removed from the site of the
work, and the contractor shall furnish and drive a new pile to replace the
damaged one. Piles pulled out and found to be in a sound and satisfactory
condition shall be re-driven and in such a case payment for both the initial
driving, pulling out and re-driving shall be made to the Contractor.
CUT-OFF
A pile which cannot be driven
to the required depth of penetration because of an underground obstruction
shall be pulled out, the obstruction removed, and the pile re-driven - all at
the contractor's expense. If for any reasons It Is not possible to drive a pile
to the required depth of penetration, the Engineer-in-charge shall determine,
whether an acceptable friction bearing capacity has been attained and, if so,
shall permit the contractor to cut the pile off perpendicular to the axis of
the pile at the cut off, elevation as shown on the drawing. Otherwise, the
contractor shall continue to drive the pile or pull out and re-drive the pile
In order to obtain the required depth of penetration.
The cut-off method shall be
used in a way that does not damage the portion of the pile to be left In place
nor the pile reinforcement.Tops of piles shall be embedded in the concrete
footing as shown on the Drawings.Concrete piles shall, when approved by the
Engineer-in-Charge, be cut off at such a level that at least five (5) cm of
undamaged pile can be embedded in the structure above. If a pile is damaged
below this level, the Contractor shall repair the pile to the satisfaction of
the Engineer-in-Charge. The longitudinal reinforcement of the piles shall be
embedded in the structure above to a length equal to at least (40) times the
diameter of the main reinforcing bars. The distance from the side of any pile
to the nearest edge of the footing shall not be less than twenty (20) cm.
When the cut off elevation for
a pre-cast concrete pile, or for a cast-in-place concrete pile is below the
elevation of the bottom of the pile cap, the pile may be built up from the butt
of the pile to the elevation of the bottom of the cap by means of a reinforced
concrete construction.
SPLICING
Piles should be lengthened when
so required, by splicing after getting approval of the Engineer-in-charge. For
this purpose the longitudinal reinforcement of the pile shall be exposed for a
length equal to at least 50 diameters of the bars. If necessary, the concrete
shall be cut away to accomplish this. Bars of the same size and of a length
sufficient for the required extension shall be fastened to the exposed bars and
transverse reinforcement as shown on the drawing for the pile head; concrete
cuts shall be made perpendicular to the axis of the pile; and all concrete
shall be removed above the elevation of the 50 diameter length cut. Bars shall,
be lapped for the full length of the bars exposed. Alternatively the splicing
can be done by welding the reinforcement bars if approved by the
Engineer-in-charge. In such cases only enough concrete shall be removed to
provide adequate working space for the welding operation.
When reinforcement has been
properly placed by lapping or welding the top of the pile shall be roughened
and the necessary form work placed. Immediately before pouring concrete, the top
of the concrete shall be thoroughly wetted and covered with a thin coat of neat
cement mortar. Concrete of the same quality as that used to cast the pile shall
then be placed finished and cured as specified for all piles, except that forms
shall remain in place for at least 72 hours after placing the concrete. Driving
of a spliced pile shall not be resumed till it is approved by the
Engineer-in-Charge.
LOADING TESTS OF PILES
The loading tests on Piles shall comply with the requirements of
Sub-section 7.2.6.
The Contractor shall keep
accurate records of all the works accomplished under this Section. All such
records shall be preserved in good condition and order by the Contractor until
they are delivered and accepted by the Engineer-in-Charge. The Engineer-in-Charge
shall have the right to examine such records at any time prior to their
delivery to him.
The following information shall be included in the records.
a)
Pile number, location and elevation of top of pile.
b)
Total depth of pile
c)
Quantity of concrete and steel used for the construction of each
pile
d)
Quantity of constituents for
each batch of mix, water cement ratio and the result of all quality control
tests.
e)
Date and time of load testing
of piles, load and settlements readings during the loading and unloading of the
test piles (For test piles only).
f)
Graph of time-load-settlement relationship for test (For test
piles only).
g)
Remarks concerning any unusual occurrence during load testing of
piles.
Items (a) to (d) shall be
reported on a format approved by the Engineer-in-Charge. The items (e) to (g)
should be reported on forms.
The presence of
Engineer-in-Charge's representative or the keeping of separate records by his
representative shall not relieve the Contractor of the responsibility for the
work specified in this clause. Payment shall not be made for any work for which
records have not been furnished by the Contractor.